(Casper, WY – May 26) Workers building the Equality Pipeline for Bridger Pipeline LLC have now strung nearly 180 miles of pipeline, nearly 94% of the total length of the 191-mile line. The Equality Pipeline will run from Hulett, Wyoming to Guernsey and carry about 200,000 barrels of oil a day once complete. “It is […]
Bridger Expansion
Bridger Pipeline Expansion Update
Construction is well underway for the Equality Pipeline being built from Hulett, Wyoming to Guernsey. Bridger Pipeline’s contractors have strung more than 30 miles of pipeline and are working in two locations along the 191-mile pipeline route. Construction started in November 2019 and is expected to be completed sometime in mid-2020. Bridger Pipeline is expanding […]